Construction management: business justification
The business justification stage is the first stage. It takes place once a business need has been identified which might result in a building project. The stage involves assessing whether there is justification for the project, preparing a preliminary business case and creating an organisational structure for the project. The business justification stage takes place before the selection of the consultant team, so the client may wish to appoint independent client advisers to help them.
In this work plan we suggest the construction manager is appointed on completion of concept design. Earlier or later appointment will result in some activities being re-allocated between the consultant team and the construction manager (for example the role of cost consultant).
Contents |
[edit] Defining the business need.
The client identifies a business need which might result in a building project and appoints a preliminary internal team to assess whether there is justification for the project.
The client prepares a statement of need, which is a first attempt to describe the possible requirements of the project. This may or may not result in the need for a project, and even if a project is necessary, it may not require a new building.
[edit] Preparing a preliminary business case.
Very experienced clients may have in-house expertise allowing them to make appointments, and to prepare a preliminary business case and strategic brief. However, many clients will not have the full range of skills required and may wish to appoint independent client advisers to assist them. These advisers are separate from the consultant team which will undertake the actual design of the project. For more information about how to appoint advisers see: Construction management: appointment.
The client explores high level options for meeting the requirements set out in the statement of need. This may include an assessment of comparable projects. They then prepare a preliminary business case, which is a first attempt to justify the investment required by the potential project and should include a management structure, draft legal agreements and funding options.
The client assesses the preliminary business case and decides whether it merits investigating in more detail and whether procedures should be established for appointing a consultant team.
[edit] Establishing an internal organisation.
The organisational structure for the project should have been defined and approved in the client's preliminary business case and may include:
- A project director.
- A project board to advise the project director on technical and user matters.
- A project sponsor responsible for day to day liaisons with the consultant team and independent client advisers.
- Champions (perhaps heads of departments) to take responsibility for the quality of the project.
- User panels to bring experience to briefing and design workshops.
- Project stakeholders to be consulted during the early stages of the project.
[edit] Preparing an initial strategic brief.
The client develops the statement of need into an initial strategic brief which provides sufficient information about the project to allow the appointment of a consultant team who will carry out feasibility studies and options appraisals, prepare a project brief and design the development.
The initial strategic brief may include the identification of potential sites for the development. It should be noted that for particularly large projects, an environmental impact assessment may be required by the local planning authority and that this may include an assessment of alternative sites for the development. It is important to consider this when assessing potential sites. Identifying possible sites, and considering their impacts (such as the possibility of moving staff) can be a complicated process and may require the appointment of independent client advisers (such as surveyors).
The client undertakes risk assessment and value management exercises, sets an initial budget for the project and considers funding options for the project. They may then revise the preliminary business case and strategic brief.
[edit] Assessing whether there is sufficient justification to progress to the next stage.
The client considers the preliminary business case and strategic brief and decides whether to proceed to the next stage where the consultant team will be appointed, feasibility studies undertaken, and options assessments carried out.
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.